Primary Separation Cells

Details

Owner: CNRL Horizon
General Contractor: Krupp
Sector: Industrial
Region: Alberta
Business: Structural
Service: Steel Fabrication, Steel Installation
Date: 2013
Location: Fort McMurray, Alberta

Utilized pre-fabricated panels which were test fit in Supreme’s assembly yard and transported to site.

Supreme Steel developed the procedure utilized for the pre assembly, transportation and site installation.  This scope of work included 131,000 man hours of fitting/welding on internal bracing and transportation frames which in turn where utilized for welding platforms during final installation.

Highlights

  • The execution strategy utilized pre-fabricated panels which were test fit and transported to site.